Project resolutions – GradSchoolPapers.com

role of love in a philosophical life, according to Diotima – GradSchoolPapers.com
July 1, 2021
What hazards are present in the natural, built, and social environments in this situation? What health effects, if any, are these hazards causing?
July 1, 2021

Project resolutions – GradSchoolPapers.com

1A. YOU HAVE PROVIDED CONSULTING SERVICES FOR A CLIENT DURING THE
PAST 10 YEARS. THE CLIENT WOULD REALLY LIKE TO GIVE YOU A 5-DAY
ALL EXPENSES PAID TRIP TO LAS VEGAS TO SHOW THEIR APPRECIATION
FOR YOUR EFFORTS IN GETTING THEM OUT OF THEIR MOST RECENT
LAWSUIT. IS IT ETHICAL TO ACCEPT THIS TRIP?
(5) YES
NO
1B. UNDER WHAT CIRCUMSTANCES WOULD IT BE ETHICAL FOR YOU TO ACCEPT
(5) THIS TYPE OF GIFT:_________________________________________________
________________________________________________________ _________
1C. IS IT ETHICAL TO TAKE THE BODY LOTION OUT OF THE HOTEL FOR YOUR
PERSONAL USE AT HOME:
(5) YES
NO
2. THE COST AND SCHEDULE ESTIMATE FOR A PROJECT SHOULD BE DEVELOPED
STARTING IN THE _________________________ STAGE?
(10) FEASIBILITY
PREPARATION OF DRAWINGS
REVIEW OF THE FINAL CONTRACT DOCUMENTS
3. WHAT ARE THREE BASIC ELEMENTS ON A SET OF CONTRACT DRAWINGS?
PLAN SHEETS:
(10) __________________________________________________________
__________________________________________________________
__________________________________________________________
CROSS-SECTIONS
(10) __________________________________________________________
__________________________________________________________
__________________________________________________________
-2-
CE 3361 PROJECT III FALL 2016 NAME:____________________
DATE:_____________________
NEAT AND PROFESSIONAL WORK
4. CAREFULLY ILLUSTRATE THE DESIGN/CONSTRUCTION MANAGER CONTRACT
MODEL DESCRIBED AND ILLUSTRATED IN THE CE 3361 CLASS.
(30)
5. LIST THE FIVE STAGES IN A PROJECT:
(20) _______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
6. ON DRAWINGS, YOU SHOULD ____________USE A DESCRIPTIVE SCALE SUCH AS
1 IN. = 10 FT ALONE
(10)
NEVER ALWAYS
SOMETIMES OCCASIONALLY
-3-
CE 3361 PROJECT III FALL 2016 NAME:____________________
DATE:_____________________
NEAT AND PROFESSIONAL WORK
7. LIST THE OVERALL PROCEDURES USED TO DEVELOP AN ENGINEERING COST
ESTIMATE AND SCHEDULE
(20)
____________________________________________________________
_____________________________________________________________
_____________________________________________________________
_____________________________________________________________
8. ISU HAS DECIDED TO CONSTRUCT A NEW ENGINEERING LAB. THE
BUILDING HAS THE FOLLOWING CHARACTERISTICS;
BUILDING PLAN: 40 FT X 80 FT
BASEMENT EXCAVATION DEPTH: 10 FT
SUPPORTED VERTICAL SLOPES ON ALL SIDES
PLAN
N
100 FT
50 FT
EXCAVATED AREA
80 FT CROSS-SECTION
10 FT
100 FT
8A. THE TOTAL VOLUME THE EXCAVATION IS MOST NEARLY?
(30) A. 1,550 YD3
B. 1,850 YD3
C. 2,150 YD3
D. 7,214 YD3
8B. ACTIVITY SEQUENCE LIST OF ACTIVITIES
ACTIVITY
NUMBER ACTIVITY
DESCRIPTION
1
MOBILIZATION
4
(20) PLACE ACTIVITIES IN APPROPRIATE CONSTRUCTION SEQUENCE
8C. COST/SCHEDULE ESTIMATE
FILL IN THE COMPLETE COST/SCHEDULE ESTIMATE
WHERE APPROPRIATE USE THE MEANS ESTIMATING HANDBOOK SHEETS
PROVIDED SEPARATELY IN MOODLE
ACTIVITY
NUMBER UNIT QUANTITY UNIT
COST TOTAL
COST UNIT
TIME DURATION
LS 1 50,000 50,000 14 14 DAYS
2 EA 1 228 228 4 1 DAY
AC 1.2
AC 1.2
CY 90 2.00
6 CY 1040
ESTIMATED COST:_____________ USD
ESTIMATED DURATION:_____________DAYS
-5-
CE 3361 PROJECT III FALL 2016 NAME:____________________
DATE:_____________________
NEAT AND PROFESSIONAL WORK
8D. CONSTRUCT A SEQUENTIAL BAR CHART SCHEDULE OF THE SIX
CONSTRUCTION ACTIVITIES. SUBMIT AS A SEPARATE DIAGRAM.
USE THE FOLLOWING FORMAT. THIS IS AN ONLY AN EXAMPLE NOT THE
ANSWER TO QUESTION 8D.
ACTIVITY TIME (CALENDAR DAYS)
M T W T F S S M T W T F S S M
HOLDING WALLS
SHRUBS
USE LONG DIMENSION OF SHEET(S).
8E. HOW MUCH SHOULD ISU HAVE TO PAY FOR THIS PORTION OF THE PROJECT?
(20) A. $220,000
B. $225,000
C. $235,000
D. $240,000

 
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code "Newclient" for a 15% Discount!

NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.

Buy Custom Nursing Papers